Paul Lyngdoh Defends Shillong Peak Ropeway Amid Ongoing Protests

Shillong: Former Tourism Minister Paul Lyngdoh defended the Shillong Peak ropeway project on Thursday, insisting that environmental clearances were locked in back in 2022. Lyngdoh, the MLA for West Shillong, claimed the approval process kicked off before he joined the Meghalaya Legislative Assembly. He also noted that local Dorbars raised no objections to the plans.

The project hit a wall with the Joint Action Committee. The group met with the Tourism Department on Thursday but failed to reach a deal. The committee demands the project move away from Lum Shillong to protect trees and local water sources. JAC secretary Dr. Linda Marbaniang claims residents were kept in the dark and denied a public hearing. "We are firm in our message that we will not stop this agitation," she said.

Lyngdoh maintains that the government did its homework. He pointed to the President of India attending the foundation stone ceremony as proof of the project's legitimacy. "The environmental clearances were the first step that was taken in 2022, when I was not even a member of the Assembly," he explained. While he stands by the work, he admitted that official communication with the public has been poor.

The standoff shows no signs of cooling down. The committee scheduled a peaceful protest rally for 10 am on October 17, marching from the last stop in Laban to the Sericulture Farm project site. Tourism Director Brenda Pakyntein plans to submit a report on the meeting to the state government. For now, the protests continue.

Updated at 17th October 2026 at 1:48am

Tourism Commissioner and Secretary Rosetta Mary Kurbah stepped in Friday to address the bureaucratic paper trail. She confirmed the state secured clearances from the Forest Department, the Airport Authority, the Indian Air Force, and the Indian Army. Kurbah added that the local Dorbar Shnong signed off on a No Objection Certificate after the government issued notice for a public hearing, which an elected representative attended.

Addressing the environmental friction, Kurbah admitted that 544 trees face the axe along the 900-metre route. The state plans to plant ten times that number elsewhere, offering to reforest land in Raid Laban Pyllun if space is provided. Designers also reworked the project to save the watershed. By lifting tower heights from 25 to nearly 40 metres and moving away from water sources, the government claims they have mitigated the risk to local catchment areas.

Kurbah noted the project has been public knowledge since 2015, with the foundation stone laid in 2024. She framed the ropeway as a necessary engine for local jobs and longer tourist stays, while urging the Joint Action Committee to keep their upcoming protest march orderly.

Updated at 17th October 2026 at 5:49pm

The Joint Action Committee is upping the ante. Following a recent meeting with the Tourism Department, the group slapped the government with an October 26 deadline to scrap the project entirely, threatening to ramp up their agitation if officials don't back down. The JAC remains unconvinced by the government's stance, citing lingering doubts about the public consultation process.

Addressing specific environmental fears, officials confirmed that a previous version of the Detailed Project Report was junked because it sat too close to a water source. The revised plan now includes six towers with smaller footprints, greenery around the sites, and a retaining wall near the first tower. The upper station will anchor at Shillong Viewpoint, while the second sits on a former nursery site. The Public Health Engineering Department and municipal authorities have signed off on these changes, claiming the new alignment keeps the water catchment area safe.

Updated at 18th October 2026 at 9:48am

The protest momentum gained a heavy hitter on Saturday when former Chief Secretary Barkos Warjri joined the movement. Warjri sided with residents, arguing that true development requires guarding natural resources rather than building over them. He warned the state against stripping away the city's ecological base for construction.

Dr. Linda Marbaniang signaled a sharp shift in tactics for the Joint Action Committee. If the government ignores their October 26 deadline, the committee plans to escalate their resistance. Beyond continued rallies, the group is weighing a hunger strike and a potential legal challenge in the Meghalaya High Court.

Updated at 18th October 2026 at 5:47pm

Beyond the looming court battle and potential hunger strike, protesters are digging into the paper trail. JAC members claim they were forced to file Right to Information applications just to drag official project documents into the light. The committee also challenged the legitimacy of the project's paperwork, questioning whether the government actually secured a valid trading licence in addition to the contested No Objection Certificates.

Warjri hit hard during Saturday's rally, framing the struggle not just as a policy dispute, but as a fight for the city's future. He dismissed the government's development pitch as a hollow justification for clearing land. "Development is not only construction. Preserving what we already have, preserving our wealth, that is development. We cannot destroy what we already have," he said. He added that his commitment to the local environment is personal and something he cannot simply discard.

Disclaimer: The views and facts expressed here are solely those of the independent citizen journalist, researcher, and others, who assumes full responsibility for the content's accuracy and legality. Any third-party media (images, videos, or audio) used belongs to its respective owners and is shared strictly for reporting, criticism, or review under the "Fair Dealing" provisions of Section 52 of the Copyright Act, 1957 (India). NEWire.in does not claim ownership over such material and reserves the right to review, moderate, or remove content at its sole discretion upon receiving valid legal concerns or grievances.