Khasi Council Shuts Down Shillong Peak Ropeway Construction

Photo Courtesy: India Today Group

Shillong: The Khasi Hills Autonomous District Council (KHADC) slammed the brakes on the Rs 151-crore Shillong Peak ropeway project on October 27. Officials locked the construction site after council members confronted representatives from the joint venture partners, KEC International Ltd and Tantia Construction Ltd.

Chief Executive Member Winston Tony Lyngdoh spearheaded the shutdown. The council claims the developers ignored local laws by starting work without a mandatory trading licence. They also failed to secure a No Objection Certificate from Hima Mylliem, the area's traditional administrative body. Heavy machinery arrived on site before any paperwork cleared.

"Our enforcement team have come twice to serve notice and also got verbal assurance from the operators. However, we realised that these people went ahead with construction without respecting the local authorities," Lyngdoh said.

The Meghalaya Tourism Department insists they followed proper channels, noting they secured an NOC from the Raid Laban Dorbar Shnong. They admitted the developer’s KHADC trading licence is still pending. The state project, which President Droupadi Murmu virtually launched on January 16, 2024, received funding from the New Development Bank and the Prime Minister’s Development Initiative for North Eastern Region. It costs Rs 151 crore, split between an Rs 80.89 crore bank loan and Rs 70.11 crore from the central scheme.

Construction work officially kicked off on October 15, 2025. The project aims to link Madan Laban to the Shillong Viewpoint using a monocable gondola system. Government officials argue the cable car will slash traffic congestion and create jobs. They also contend the path avoids the Umiew water catchment area. Local activists and environmental groups remain skeptical. They fear the development will ruin forests and threaten community rights.

Updated at 28th October 2026 at 9:47am

The council previously flagged the project in May and September, serving two show-cause notices. Despite a written assurance of compliance on September 15, the developers failed to produce the necessary paperwork. During the site shutdown, company managers claimed they were only performing preparatory work, but the KHADC dismissed the defense, ruling that pre-construction activities do not bypass legal requirements. The site will stay locked for at least seven to 10 days, pending the submission of outstanding documentation.

The project, which also counts French ropeway specialist POMA as a technical partner, is now under tighter scrutiny. CEM Winston Tony Lyngdoh stated the shutdown signals a more aggressive enforcement strategy, promising that the council will hunt down and penalize other companies ignoring local rules.

Updated at 28th October 2026 at 6:15pm

The shutdown followed a string of failed deadlines. Records show the KHADC issued show-cause notices in May and September, but the developers failed to produce the necessary documents despite a written commitment to comply by September 15. During the site seizure, company managers tried to argue that the activity on the ground was limited to levelling and preparatory work rather than full-scale construction, but the council rejected the excuse, ruling that any work requires proper legal standing.

The project, which ropes in French firm POMA as a technical and equipment partner, remains under a strict stop-work order. CEM Winston Tony Lyngdoh warned that the council will hunt down and penalize other firms ignoring local rules, signaling an aggressive new enforcement strategy meant to force outside contractors to fall in line with tribal authority.

Updated at 29th October 2026 at 9:47am

The conflict escalated on Wednesday when the state government filed an FIR at Laban Police Station against the KHADC inspector who seized the project site. Commissioner and Secretary of the Tourism Department, R.M. Kurbah, stated the action targets the individual, not the council as an institution. Kurbah insisted the Madan Laban site is government property housing a temporary camp for soil testing and road development, asserting that no actual construction or foundation work has commenced.

Addressing the licensing dispute, Kurbah provided a timeline of the contractor’s efforts, noting they received a NOC from the concerned Dorbar on May 4, 2026, and applied for the trading licence on May 18. She added that subsequent clearances were secured, including approval from the Dorbar of the five shnong and eleven Kur of Laban-Mylliem on September 28. The state government maintains no decision has been made to suspend the project and will continue negotiations.

Leader of the Opposition, Mukul M. Sangma, weighed in on the impasse, urging both the state government and the council to drop the confrontation in favor of constructive dialogue. Sangma warned that a lack of coordination between authorities creates jurisdictional chaos and insisted that public concerns must be handled through collective engagement rather than unilateral enforcement.

Updated at 29th October 2026 at 1:49pm

The conflict heated up Wednesday after the state government lodged a formal complaint at the Laban Police Station against the KHADC inspector who padlocked the site. Tourism Commissioner R.M. Kurbah confirmed the move, clarifying the FIR targets the official's actions rather than the council as a whole. Government lawyers are currently weighing legal options to reclaim control of the Madan Laban grounds.

Kurbah defended the activity on the ground as essential site prep for New Development Bank environmental audits, including soil testing and road leveling, insisting no structural foundations for the six pillars exist yet. She also laid out a detailed timeline of the contractor’s paper trail, noting they sought clearances from the Syiem of Hima Mylliem and various Dorbars starting in mid-2026. Meanwhile, the Joint Action Committee opposing the project took its fight to the Syiem of Hima Mylliem, demanding he revoke the land leases granted to local headmen.

Updated at 29th October 2026 at 7:00pm

Tourism Commissioner R.M. Kurbah clarified that the FIR targets the individual inspector specifically, rather than the council as a governing institution. The government is now pursuing legal avenues to regain possession of the Madan Laban land.

Kurbah defended the site activity as essential compliance for New Development Bank safeguards, specifically citing soil testing and road leveling requirements. She explicitly stated the proposed ropeway towers sit along a ridge roughly 3.15 kilometers from the Lum Shillong water catchment area, a distance she claims mitigates the environmental risks cited by activists.

Opposing the state's stance, the Joint Action Committee escalated their pressure by meeting the Syiem of Hima Mylliem on Wednesday. They are pushing for the formal cancellation of land-lease sanads previously granted to local headmen for the project site.

Disclaimer: The views and facts expressed here are solely those of the independent citizen journalist, researcher, and others, who assumes full responsibility for the content's accuracy and legality. Any third-party media (images, videos, or audio) used belongs to its respective owners and is shared strictly for reporting, criticism, or review under the "Fair Dealing" provisions of Section 52 of the Copyright Act, 1957 (India). NEWire.in does not claim ownership over such material and reserves the right to review, moderate, or remove content at its sole discretion upon receiving valid legal concerns or grievances.