Kohima: The Gauhati High Court ordered an independent inspection of the stalled Chakhabama-Kikrüma road segment. This stretch is part of the Kohima-Jessami road, known as Package-II. The court formed a two-member committee to evaluate the site after the contractor reported significant delays. Justice Robin Phukan and Justice Yarenjungla Longkumer issued the order on November 25.
M/s Ratna Infrastructure Projects Pvt Ltd, the lead contractor, claims it lacks work sites. It blames the National Highways and Infrastructure Development Corporation Limited (NHIDCL) for stalling on Change of Scope proposals. These changes cover the Chakhabama Military Area, pavement repairs, and four sinking zones. The contractor says these adjustments total Rs 36,49,15,116.10, which is over 50 percent more than the original Rs 69 crore price tag.
The contractor noted it completed all work in clear zones. It maintains it will file a timeline within seven days of getting approval for the new scope. Regarding the delays, the contractor stated, "The lack of approval had left it without adequate work fronts to execute the remaining works."
The court-appointed committee includes Advocate Joshua Sheqi and a senior engineer from the Nagaland PWD. This engineer must have had no prior role in the project. They must physically inspect the site, check equipment and manpower, and review the necessity of the proposed changes. The team will submit a report with photos before the next hearing.
NHIDCL must pay all inspection costs. The agency must also turn over project records, including the contract agreement and progress reports. The court ordered the NHIDCL Executive Director and the project engineer to attend the next hearing. The court will resume the matter on February 10, 2027.