Shillong: Crews are pushing ahead on the 38-km Shillong Western Bypass. Work spans all three construction packages despite early trouble on the job site. Progress remains steady across the board.
Package-I leads the pack with 71% of the work finished. Package-III sits at 51% completion, and Package-II trails slightly at 47%. The project aims to drain traffic away from the city streets. It provides a vital route to cut congestion and speed up local travel.
Official data confirms the status of these stretches. "Construction of the 38-km Shillong Western Bypass is progressing across all three packages despite initial execution challenges," according to recent reports. The new road will take heavy pressure off the current network once finished.