Shillong: The Supreme Court ended the legal fight for BSC-C&C JV and BSCPL Infrastructure Ltd. Justices M.M. Sundresh and Prasanna B. Varale dismissed the firm's petitions. This decision confirms a five-year ban from all state work. The Meghalaya government issued the initial debarment on December 3, 2024.
Trouble started with a road project. The Ministry of Road Transport and Highways greenlit the Shillong-Nongstoin section of NH-44E and the Nongstoin-Rongjeng-Tura road in 2009. The work fell under the Special Accelerated Road Development Programme for the North-East. BSC-C&C JV won the bid in February 2011. The budget ballooned. Costs jumped from Rs 1,303.83 crore to Rs 2,406.46 crore by the time the project finished in December 2017.
The contractors eventually demanded Rs 487 crore in delay costs. They submitted internal ledgers as proof. Auditors found a Business Promotion account instead. It listed watches, liquor, laptops, cameras, and mobile phones gifted to officials. The firm even paid for hospitality meant for the Dispute Review Board. The Chief Engineer of PWD Roads filed an FIR at the Sadar Police Station in East Khasi Hills in September 2024.
The joint venture fought the blacklist in court. They claimed the state lacked authority after the job ended. They called the gifts simple welfare expenses. Judges rejected these excuses. The High Court of Meghalaya dismissed the case in December 2025. A Division Bench led by Chief Justice Revati Mohite Dere and Justice Wanlura Diengdoh upheld that ruling in February 2026. The court noted: "The state is under an obligation to put public interest over everything else. After all, the monies utilised are public money, which cannot be lost sight of."
Advocate General Amit Kumar defended the state. He led the legal team through the Arbitral Tribunal and up to the Supreme Court. The criminal case from the 2024 FIR remains active.